Installed Gross MWh = Deliverable Net MWh / [ DoD × RTE_AC × SOH_EoL × (1 - Aux_parasitic) ]
Worked Numerical Example (50 MW / 200 MWh 4-Hour System at Year 10):
- Target Deliverable at 220kV Grid Bus: 200 MWh
- Depth of Discharge (DoD): 90% (0.90)
- AC-to-AC Round-Trip Efficiency (PCS + Transformer + Cell): 86% (0.86)
- End-of-Life State of Health at Year 10 (SOH_EoL without augmentation): 75% (0.75)
- Auxiliary parasitic cooling & BMS load: 3.5% (0.035 → factor 0.965)
Installed Gross MWh = 200 / [ 0.90 × 0.86 × 0.75 × 0.965 ] = 200 / 0.560 = 357.1 MWh
To avoid an unviable 357 MWh initial capital outlay, the engineering practice implements a 240 MWh initial build + 30 MWh augmentation at Year 5 + 30 MWh at Year 10, reducing Day-1 CAPEX by over ₹120 Crore.