The VGF scheme is structured as a capital grant to bridge the viability deficit between pure merchant arbitrage economics and long-term utility capacity procurement. Grants are disbursed in performance-linked tranches:
Tranche 1: 20%
Released upon financial closure and award of equipment supply contracts for major battery enclosures and PCS.
Tranche 2: 40%
Released upon complete delivery of battery containers, civil casting of foundations, and arrival of step-up transformers on site.
Tranche 3: 40%
Released upon statutory CEIG charging approval, trial commercial run (COD), and 30 consecutive days of continuous grid availability.